Hazardous Zonal assessments
Over 450 zonal assessments carried out in the past 15 years
Burnage Associates has carried out a large number of Zonal assessments for both Large Independent Network Operators and Individual Design Consultants. We provide a 10 day turnaround based on a desktop assessment and in cases where pressure and inspection time intervals cause zonal issues we provide advise on methods to reduce the zones.
The IGEM / SR / 25 Edition 2 or the IGEM / UP / 16 Edition 2 Zonal Assessment will form part of the overall DSEAR Report document required for all installations that contain hazardous materials, such as natural gas.
IGEM / SR / 25 EDITION 2
Hazardous area classification of natural gas installations
Based upon the client information provided we deliver a:
Assumptions Document
Calculations Document
Hazardous Area Drawing
Turnaround 10 working days based on desktop assessment.
IGEM / UP / 16 Edition 2
Design for NatuRaL Gas InsTAllations on industrIal and commercIaL premIsEs with respect to DSEAR
Based upon the client information provided we deliver a:
Assumptions Document
Calculations Document
Hazardous Area Drawing
Turnaround 10 working days based on desktop assessment.